Problem
A client organisation’s approach to quantitative risk analysis required cost and schedule risk to be modelled separately. Outputs were then manually interfaced to calculate the cost of delay and prolongation. The approach produced results, but it had a fundamental limitation: because cost and schedule were modelled in isolation, the correlations between them could not be properly captured. The way a delayed activity drives prolongation costs, the way a cost risk affects the viability of a schedule assumption — these relationships were approximated rather than modelled, and the picture of risk that resulted was systematically incomplete.
Beyond the technical limitation, the process was slow. Existing customer assurance and management requirements enforced a bottom-up rebuild of modelling artefacts at each cycle, rather than allowing iterative refinement of a live model as the programme’s risk profile evolved. Through-life estimating — adapting budgets progressively in response to a changing and volatile supply chain environment — was effectively impossible.
Challenge
The scale of what needed to change ran across every dimension that a capability initiative depends on.
People and Process: No internal training had been delivered on integrated cost and schedule risk analysis methods. Different teams had built their own bespoke cost models in different ways, producing silos of data and inconsistent approaches with no shared standard to build from. Processes did not exist to support an integrated workflow; the existing ones actively required the separate approach to be maintained.
Technology and Partners: The software required for integrated quantitative cost and schedule risk analysis had not been acquired, and the organisation had no experience of tools capable of delivering it. Programme partners were contracted on existing deliverables and had neither the incentive nor the contractual basis to develop new procedures that would benefit the wider programme. The gap between where the organisation was and where it needed to be was significant — and no one in the existing supply chain was positioned to close it.
Solution
Kaleido partnered with the client’s chosen software vendor and developed the organisation’s first-ever integrated Quantitative Cost and Schedule Risk Analysis (iQCSRA) model in Safran Risk, built from existing project data and artefacts.
Building the Integrated Model
Rather than waiting for perfect conditions, we worked from what existed: current cost and schedule data, existing risk registers, existing project artefacts. The integrated model produced an immediate and material improvement in the treatment of inflation, discrete risks, uncertainty, and prolongation costs — areas where the previous separate-model approach had been forced to rely on approximation and manual interfacing. For the first time, the client could see the full cost and schedule risk picture in a single coherent model, with the correlations between cost and schedule risks properly represented.
Creating New Ways of Working
Alongside the model, Kaleido developed the workflows and data transfer processes needed to migrate all existing separate models into the integrated approach. Documentation was produced to define how data flows from the schedule and cost model into the risk analysis, how results are interpreted and communicated, and how the model is maintained and updated through the programme lifecycle. The goal was not only to deliver a model, but to embed a new way of working that the client team could own and sustain independently.
Identifying the Path Forward
The engagement also surfaced the gaps that would need to be closed to realise the model’s full potential. Chief among these was the misalignment between the Cost Breakdown Structure and Work Breakdown Structure — a structural issue that, if left unaddressed, would constrain the model’s accuracy and limit what could be drawn from it. A capability improvement roadmap was developed: a clear, sequenced path to the next level of maturity, with iterative improvements designed to progressively deepen the quality of insight and build the confidence of decision-makers in the process and its outputs.
Conclusion
This engagement illustrates what capability uplift looks like when done properly — not as a one-off model delivery, but as a genuine shift in how an organisation approaches quantitative risk analysis. By combining technical delivery in Safran Risk with new ways of working, knowledge transfer, and a structured roadmap for continued improvement, Kaleido gave the client something more durable than a better model: the capability to sustain, evolve, and draw increasing value from integrated cost and schedule risk analysis through the life of the programme.